Skip to content
Home Renovation Guru Renovation plans, material schedules and the
Structure & Layout

How Do You Plan Drainage Falls in a Rear Extension?

How Do You Plan Drainage Falls in a Rear Extension?
Photo: Wikimedia Commons (Public domain) — illustrative view, not the exact property described.

Plan the falls first, then the floor level, then the finished ceiling height, because the drain has to fall at 1 in 40 to 1 in 80 towards the existing sewer and that depth has to fit inside the floor zone. In practice a rear extension needs 150 to 300mm of floor build-up for drainage, insulation and screed.

The mistake is designing the extension to match the existing floor level and then discovering the drain cannot reach the sewer at that level. The drain always wins, because gravity cannot be adjusted.

What fall does a new drain need?

1 in 40 to 1 in 80 for a 100mm pipe, which is 12 to 25mm per metre. Over a six metre rear extension that is 75 to 150mm of fall before the connection depth is counted.

Fewer bends is as important as the fall. Two 45-degree bends are better than one 90-degree bend, and a straight run is better than either.

How deep does the connection need to be?

Deep enough to fall to the sewer, which is usually 600mm to 1.2 metres below ground. The new extension floor has to sit above that, plus the insulation and screed.

A CCTV survey of the existing drain establishes the invert level. Without it, the design is a guess.

Can a pumped solution be used instead?

Yes, for a basement or a very long run, but it adds a serviceable item that fails eventually. For a rear extension, gravity drainage is the normal answer.

A pump also needs a power supply, an alarm and access. It is a maintenance commitment, not a one-off cost.

Where should the inspection chambers go?

At every change of direction, at every junction, and at intervals of no more than 22 metres on a straight run. Each chamber needs access for rodding.

A chamber inside a finished floor needs a sealed cover and a clear access route. That has to be designed into the layout, not added later.

How does the extension drainage connect to the existing system?

Through a new connection to the existing manhole or a new junction on the run, installed by a contractor approved by the sewer authority in many jurisdictions.

A connection made without approval can be refused, and the refusal happens after the floor is built.

What about rainwater?

Roof water from the extension needs its own connection, and it should not discharge into the foul system where separate systems exist. Soakaways are an alternative where the ground allows.

Combining surface and foul water is a common error on renovations, and it is one the authority will ask about.

Does the drain need ventilation?

Yes. The new run needs a vent or an air admittance valve at the head, otherwise the traps siphon. A stub stack with an air admittance valve inside the extension is the usual solution.

The valve has to be accessible and above the flood level of the highest fixture. A valve buried in a wall is a future problem.

How is the drain protected during construction?

With a concrete surround or a granular bed, depending on the pipe and the load above. A pipe under a driveway needs a different protection from one under a garden.

Heavy plant over an unprotected pipe is how a new drain fails in its first year.

What gradients are too steep?

Above 1 in 40, solids can separate from the water and be left behind. Very steep runs need a rest bend or a series of gentler sections.

The common failure is not too steep but too flat: a run laid at 1 in 100 because the floor level was fixed first.

How is the fall checked?

With a laser level or a dumpy level, at the pipe invert, and recorded before backfilling. A string line is not accurate enough over a long run.

Photograph the level readings with the pipe in view. That record is what the inspector accepts.

What about the floor build-up?

Drain, then insulation, then screed, then finish. A typical build-up is 150mm for the drain zone, 100mm insulation and 65mm screed, which is 315mm below finished floor.

That depth has to be accommodated at the door threshold. The transition from the existing house is where the design is tested.

Can the drain run under the extension floor?

Yes, and it is normal, provided it is protected and the access points are retained. A drain under a solid floor without a chamber is a drain that cannot be rodded.

Chambers at each end of the run solve it. The covers need to be sealed and insulated.

How does the extension affect the existing drains?

It may overload them, particularly where the extension adds a bathroom or a utility room. The existing run has to be checked for capacity and condition.

A CCTV survey before design is cheaper than a repair after the floor is poured.

What approval is needed?

Building regulations approval for the drainage, and often a separate consent from the sewer authority for the connection. Both are separate from planning permission.

The connection consent is the one people forget, and it is checked before the connection is made.

How much does extension drainage cost?

1,500 to 6,000 depending on the run length, the depth and the number of chambers. A new connection to a public sewer adds 1,000 to 3,000.

The cost is dominated by excavation and access, not by the pipe.

What goes wrong most often?

The floor level is set first, the drain is laid at an inadequate fall, and the extension drains slowly for years. The second is a missing vent, which produces gurgling and smell.

Both are free to avoid at design stage and expensive to correct after the screed is poured.

How should the drainage drawing look?

A plan with pipe sizes, gradients, invert levels, chamber positions and the connection point, plus a section showing the fall relative to the finished floor.

The section is the drawing that proves it works. A plan alone hides the problem.

What fall does a garden drain need?

1 in 60 to 1 in 80 for a 100mm pipe, and 1 in 40 for a 75mm run serving a single outlet. A long garden run needs a chamber at the change of direction.

Garden drains fail quietly: the fall is set by eye, the pipe settles, and the first sign is a soggy patch two winters later.

Can the drain be rerouted later?

Only by breaking the floor, which means removing the finish and the screed. It is the least accessible service in the building.

That is the argument for getting the survey and the design right first. The guide on adding a bathroom without drainage covers the feasibility test.

Drainage is the first service to design and the last to be able to change. The guides on bathroom drainage and on basement lowering cover the same constraint at different scales.

Keep reading

Related guides